To judge whether a colocation site can actually host AI or other high-density workloads, ask for evidence of energized, contractually committed power and a dated commissioning plan, not just a megawatt figure on a spec sheet. Then score each candidate on the same five areas: deliverable power, cooling, expansion rights, commissioning schedule and electrical-equipment reliability. If a site cannot document those answers, a cloud or hybrid approach is usually the lower-risk choice until it can.
This article gives mid-sized buyers a question-by-question scoring sheet. It deliberately ignores price per rack, because a cheap rack that arrives late, or can’t be cooled at the density you need, costs more than it saves.
Why capacity claims need a readiness test
AI conversations tend to center on infrastructure headline numbers. A recent Network World feature summary notes that the discussion has focused on tokens, gigawatts and GPUs, with security rarely leading. Headline capacity is not the same as capacity you can use on your timeline.
Power delivery and commissioning are where schedules can slip. Coverage on TechTarget describes Schneider’s claim that software-defined medium-voltage switchgear can speed equipment delivery and commissioning for AI data centers, while operators scrutinize reliability and cybersecurity. That is a vendor claim, and the site’s front page changes often, so treat it as a prompt for questions rather than proof. Ask any provider which electrical architecture it uses, what evidence supports its schedule, and how the equipment is secured and maintained.
Key takeaway: Marketing describes what a campus is designed to support. Your contract should describe what is energized, cooled, tested and reserved for you, and by when.
The five-part colocation readiness framework
Each area below has questions that separate a documented answer from a sales answer. Score each question 0 to 3 (see the scoring method further down).
1. Deliverable power
- Is the power you need energized today, under construction, or planned? Get the status in writing for your specific suite or hall.
- Is the quantity contractually committed to you, or only available on a first-come basis?
- What is the utility feed status: signed agreements, upgrades pending, or still in study?
- What density per rack and per row does the contract support, and is it measured in sustained or peak load?
- What redundancy design applies to your load (for example, N+1 versus 2N), and does it hold at your full density?
2. Cooling approach
- Is the proposed cooling air-based, rear-door, direct-to-chip liquid, or a mix? Which is already operating in production at that site?
- If you plan to adopt liquid cooling later, are the piping, heat rejection and floor loading already provisioned, or would retrofitting delay you?
- Who is responsible for the facility-side loop versus your equipment, and who handles leaks, monitoring and maintenance?
- Does your hardware vendor support the provider’s cooling design and approved fluids or temperatures?
3. Expansion rights
- Do you hold a right of first offer or a reserved expansion block, and what does it cost to hold it?
- Is expansion space adjacent to your initial footprint, or in a different hall with different power and cooling characteristics?
- What happens to your reservation if the provider re-allocates capacity to another customer?
- Can you convert some reserved capacity between lower and higher density?
4. Commissioning timeline
- What are the milestones between signature and handover: equipment delivery, energization, integrated systems testing, your acceptance?
- Which long-lead items (switchgear, transformers, generators, cooling plant) are already on site versus on order?
- What remedies exist if handover slips: credits, termination rights, or nothing?
- How does the provider run integrated testing under load, and can you witness it?
5. Electrical-equipment reliability and security
- What is the maintenance history and support model for the switchgear and power distribution serving your hall?
- If the provider uses software-defined or network-connected power equipment, how is it segmented, patched and monitored? Operators are scrutinizing this, and so should you.
- Who has remote access to building management and power systems, and is that access logged and reviewed?
- Can the provider share recent audit or assurance reports covering these systems?
For the security questions, your cybersecurity team should review the answers alongside facilities staff. Our cybersecurity solutions overview shows how MoJo approaches that kind of review.
How to score and compare sites
Use a simple, repeatable method so that sales presentations don’t drive the outcome.
- Send the same question set to every provider and ask for written answers.
- Score each answer 0-3. Zero means no answer or marketing language only. One means verbal assurance. Two means written commitment without supporting evidence. Three means written commitment with evidence such as an energization schedule, test plan or signed utility documentation.
- Weight the areas to match your project. A reasonable starting point is power 30%, commissioning 25%, cooling 20%, reliability and security 15%, expansion 10%. Adjust if, for example, you expect to triple capacity within two years.
- Apply gates before totals. A score of 0 on committed power or on handover dates should disqualify a site for an AI deployment with a firm launch date, regardless of its total.
- Re-score after clarifications and note where a provider’s answer changed between conversations.
A hypothetical example
This example is illustrative only and does not describe a real provider. Suppose a mid-sized company wants to deploy a GPU cluster within a year. Site A scores high on cooling because it already runs liquid-cooled halls, but its power for your hall is planned, not energized, and the handover date is verbal. Site B has lower-density cooling but energized, committed power, a written milestone schedule and a reserved expansion block.
Site A’s gate failure on power and commissioning would exclude it for a firm-date launch, even though its total might look competitive. Site B may be the better fit if your first phase can run on rear-door or hybrid cooling. The scoring sheet makes that tradeoff visible instead of leaving it to instinct.
When cloud or hybrid is the lower-risk choice
Colocation isn’t automatically right for AI. Match the approach to your certainty about demand and timelines.
| Approach | Best suited to | Main risk |
|---|---|---|
| Colocation | Stable, predictable high-density demand; owned hardware; data residency or cost-control needs | Delivery and commissioning delays; hardware lead times; cooling mismatch |
| Public cloud | Experimental or uncertain workloads; short project windows; teams without facilities expertise | Usage cost growth; GPU availability; egress and lock-in |
| Hybrid | Steady base load in colocation with burst or pilot capacity in cloud | Integration complexity; network design; two operating models |
Choose cloud or hybrid first if your workload is still a pilot, if no provider can document committed power inside your window, or if your team lacks capacity to manage hardware procurement and facility coordination. Moving to colocation later, once demand is proven, is often less risky than signing early for capacity that arrives late.
Pre-signature checklist
- Written statement of energized versus planned power for your specific hall
- Contracted density, redundancy design and measurement basis
- Cooling method in production today, and the retrofit path to liquid cooling if needed
- Reserved expansion capacity, its location and the cost to hold it
- Milestone schedule with status of long-lead equipment
- Remedies for delayed handover
- Integrated testing plan, with your right to witness
- Security controls for network-connected power and building systems
- Hardware vendor confirmation that your planned systems are supported in that environment
- A fallback plan (cloud or interim capacity) if handover slips
Next step
Before you request proposals, write down your target launch date, the density you need in year one and year three, and what you would do if handover slipped by a quarter. Those three answers determine your gates and weights. If you’d like a vendor-neutral second opinion on the scoring sheet or on how to compare providers, MoJo can help through its technology service offerings.
Sources
- TechTarget: coverage of software-defined medium-voltage switchgear and operator scrutiny of reliability and cybersecurity
- Network World: coverage noting the AI infrastructure conversation’s focus on tokens, gigawatts and GPUs
Both sources are publication front pages whose featured items rotate. Verify any specific vendor claim directly with the provider before relying on it.